Traffic Infrastructure Construction for Smooth Chongqing Progressed Well from Jan. to Apr.

The traffic infrastructure construction for Smooth Chongqing this year, with total planned investment of RMB 61.07 billion, covers seven aspects, involves 115 items, according to the 2010 Plan of Traffic Infrastructure Construction for Smooth Chongqing. The investment from Jan. to Apr. has reached RMB 16.593 billion in total, accounting for 27.2% of the planned investment for the year. The progress achieved is as follows:

Urban road construction in city proper: Section A of Yu’nan Avenue was completed and open to traffic; Jiayue Jialing River Bridge is almost completed; a series of major projects progressed well, including Cimushan Tunnel, Dongshuimen Yangtze River Bridge, Qiansimen Jialing River Bridge, Shuangbei Bridge and South Liaison Avenue of the airport; the construction of 11 new projects has commenced, such as Airport Road expansion, Shuangfeng Bridge and Airport Interchange and Tongmao Avenue.

Construction of Rail Transit: for Chao-Sha Section of No. 1 Line, track laying, station decoration and equipment installation are in progress; for Sha-Da Section of No. 1 Line, the civil works have been carried out in all aspects; for Phase I of No. 3 Line, the main works has been completed and the decoration is in progress; for Phase I of No. 6 Line, the construction has been carried out in all aspects.

Construction of bus station yard and transfer hub: the main work of Nanping Central Transfer Hub has been completed, and the equipment installation and landscaping are in progress; the main works of Sigongli Transfer Hub is partially topped.

Construction of expressways: Changshouhu Tourism Expressway was completed and open to traffic on May 1; 15 continued projects, such as Fengyun Road and Wufeng Road, progressed well.

Construction of ports and waterways: Some on-going major projects, such as Jialing River Caojie Waterway and Hydropower Station Project, Cuntan Phase III project, Guoyuan Phase I project and Donggang Phase I project, progress well. For Cuntan Phase II Project, the hand-over and acceptance of multi-purpose container berth, loaded container yard and ro/ro berth have been completed.

Construction of railway: 7 continued projects, such as Yichang-Wanzhou Railway, Suining-Chongqing No. 2 Railway, progressed well; preparation work of 4 new projects, such as Sanjiang-Wansheng-Nanchuan Railway Reconstruction and Chongqing-Guizhou Railway, is in progress.

Construction of aviation facilities: Phase III expansion of Jiangbei Airport, and Qianjiang Airport project progressed well; the proposal of Wushan Airport has been submitted.

   